Anderson Way

Road upgrade moves to intersection construction

Jun 12, 2020 | 10:12 AM

A project to upgrade 48th Avenue in Vernon is into its next phase and could be completed by next month.

The work includes adding a new drainage culvert to prevent annual flooding issues, road improvements and a multi-use pathway on the north side of 48th Avenue.

The third portion (“Stage B”) of the project (between Highway 97 and 29th Street) is under construction and should be done by mid-July.

“Construction in the intersection of 48th Ave and Anderson Way is scheduled to take place between now and the middle of July. Traffic access to Anderson Way from 48th Avenue will be limited during this time,” said a city news release.