Active Living Centre construction moving into final stages
Vernon’s new recreation hub is still on track to be open in the late-fall.
A city staff report stated construction of the Active Living Centre had entered the final stages of construction, testing, commissioning and inspections.
Included in those stages will be filling the pools at the ALC to test the aquatic mechanical, filtration and air handling systems. They also need to be filled and operational before they can be inspected and approved by Interior Health.
The RDNO had provided approval for using the water system to fill the pools, which will be done during the week of September 14 in line with the end of the agricultural irrigation season demands.