ALC construction progressing on budget, though could face slight opening delay
Construction of Vernon’s new recreation centre has been making progress, though there has been a slight hiccup.
An update on the construction of the Active Living Centre (ALC) stated there was an issue that could cause a slight delay in opening the new facility.
“During the first quarter of this year, additional sanding and re-staining of the glulam beams was required, necessitating keeping the scaffolding and plywood working platform in place over the 50m pool for an additional four weeks,” the report stated.
“This has delayed the static water testing of the 50m pool tank and the start of tiling in that area. The project team will continue to look for and find efficiencies to mitigate any further delays and keep the project on target for the fall of 2026.”