Two sections of the Rail Trail complete
Two more sections of the Rail Trail through the Shuswap has been completed.
The Columbia Shuswap Regional District (CSRD) said the sections between kilometre 0.5 and 4.4 from Sicamous and from kilometre 59.15 to 50.15 into Armstrong had been completed Friday, April 3.
The North Okanagan Rail Trail section at Armstrong was open for use, though the Sicamous section was still restricted due to construction to the Bruhn Bridge. The CSRD added there was limited parking at the Sicamous Narrows trailhead.
The CSRD also stated construction of the trail along Mara Lake began earlier in the week, and was expected to take six weeks to complete.