Work ongoing to restore power at Okanagan fire areas
Progress has been made restoring power to areas ravaged by summer wildfires.
B.C. Hydro said work was ongoing in the Okanagan Indian Band land, where power had already been restored to around 2,700 customers impacted by the Bradley Creek wildfire and area windstorms.
Crews had also installed nearly 200 new power poles in the area.
“Energization of the main distribution line remains on track for Friday (August 14), with customer restorations expected to begin progressively over the weekend as distribution lines are rebuilt off the mainline and re-energized,” the utility provider stated in a release.