Stickle Road Saga Nearing End
It’s taken more than six months, but an upgrade to Highway 97 and Stickle Road north of Vernon should be done by the end of this month.
The Transportation and Infrastructure Ministry says the finishing touches are being put on the intersection project.
“Paving was completed at the end of October and remaining work will take place throughout the rest of this month. This includes constructing concrete medians, installing new signs and lighting, applying pavement markings, landscaping and cleaning up the construction site,” says an email from the Ministry to Beach Radio News.
The project is extending left turn lanes, installing acceleration and deceleration lanes, and removing left turns onto Highway 97.