Kal Lake Road Project To Close Road
The next phase of construction on Kalamalka Lake Road in Vernon is ready to proceed.
The City says work to add a multi use path from Browne Road to the Alpine Centre will start Monday (March 26) and continue to July 13.
There will be a full road closure on Kalamalka Lake Road from Browne Road to the Alpine Centre between April 9 and July 6 (13 weeks), 24 hours/day.
Single-lane alternating traffic will also occur, as required, from April 3 to April 9; and from July 6 to July 13.