An upgrade to Husband Road in Coldstream will go ahead this spring.
District council has awarded the contract to Nixon Earthworks for $769, 548, the lowest of two bids that were submitted.
In addition to addressing the condition of the road, the design also includes drainage improvements and widening the north side of the road to better accommodate bicycles, improving safety along the road.
A pavement assessment in 2021 by Urban Systems said that Husband Road, from Kalamalka Road to the intersection with Mariposa Place and Sunflower Place, was in very poor to failed condition.