Get the Top, Local stories delivered to your inbox! Click here to join the daily Vernon Matters newsletter.
Vernon Matters file photo (Liam Verster)
City council

Vernon staff get kudos for completing most of approved projects over last few years

May 28, 2024 | 2:00 PM

City of Vernon staff say only six approved infrastructure projects have not been completed over the past five years.

That was the figure provided to Vernon city council at their meeting Monday, May 27 after council requested a report on uncompleted projects in late March.

The report showed 82 infrastructure projects had been approved since 2019, and only six of them had been significantly delayed or deferred, as shown below.

  • Foothills Ravine Trail – $75,000: Designs were completed but the budget was insufficient to complete the stairs required at the bottom of the trail
  • Okanagan Landing Sanitary Sewer Local Area Service – $2,984,000: The local area service system was unsuccessful, and the process was changed to a municipal fee approach
  • Okanagan Landing Sanitary Sewer Local Area Service – Longacre Area – $2,060,000: The local area service system was unsuccessful, and the process was changed to a municipal fee approach
  • Dog Beach – Dog Park Upgrades – $200,000: The project had been coordinating with a proposed Regional District of North Okanagan lake intake for several years, and it was recommended not carrying over the project and reevaluating the scope and priority of the project through an updated Parks Plan once the lake intake and environmental permits are in place
  • F.B. Jacques Park Trail Connection – $200,000: Preliminary designs identified challenging topography that would require more funds to complete the work, so staff recommended deferring the project and reevaluating the scope and priority of the project through an updated Parks Plan
  • Kin Race Track Park – Phase 1 – $3,000,000: The project was rescheduled as per the 2023 Kin Race Track Athletic Park update to council, and funding was moved back to a reserve account

Upon presenting the report, Mark Dowhaniuk, Vernon’s Infrastructure Manager, told council the sanitary sewer work will not need to be pursued as it is under the municipal fee approach now. He also said the F.B. Jacques Trail and the dog beach would be reviewed again when the Parks Plan is updated, and that the Foothills Ravine Trail is expected to be included in the 2025 budget.

Mayor Victor Cumming noted the Kin Race Track work was deferred by council and the money returned to reserves until the Active Living Centre work was done.

Following Monday’s meeting, Cumming told Vernon Matters there were only two projects still awaiting funding so work could begin, the Ravine and Jacques Parks updates, and claimed those were both small projects.

“They’re two small sets of stairways and walkways between some streets in the city,” Cumming stated.

“So really, we’re down to two very small projects that were undone, which is amazing if you think of the number of projects.”

Council had initially thought there were lots of approved projects that were never started, but were pleased to learn there were only a handful of such projects.

“Good job. We’ve got 76 out of 82 projects rolling, that’s fantastic,” Councillor Brian Quiring, stated during Monday’s meeting.

“Also, what I appreciate about what you guys do is you’re pushing technology, I don’t know how many times you’ve said ‘minimal disruption.’ You guys are on it with the trench lists, repairs of the pipes, the, I don’t know what you call it, when you re-line the inside. Good job and keep up the good work.”

Council was also told Monday that a report on the status of approved infrastructure projects would be presented on an annual basis moving forward to keep both council and the public appraised of the infrastructure work.

“It’s critical, our taxes pay for about $55-million of the $100-million budget, or $105-million depending on what is was last year, so that’s really really important that [people] see what is happening with their money,” Cumming told Vernon Matters.

“Out of the $100, 105 million, this last year $29-million was in capital, so that’s a third of the big budget, so it’s really important that people know what’s happening with a third of the big budget.”

Council received the report on the infrastructure projects for information at Monday’s meeting.

View Comments