District calls on ministry to pay for creek moving project
Coldstream council is not ready to foot the bill for a costly project to re-align Coldstream Creek in the Lavington area.
At its meeting Monday, Feb. 13, council rejected a staff recommendation to proceed with detailed design, permitting, and construction of moving Coldstream Creek back to its pre‐2018 channel and restoration of the wetland.
The project is estimated to cost $450,000 with staff suggesting gas tax funds be used to pay for it.
Instead, council directed staff to send a letter to the Ministry of Forests requesting the ministry restore the creek to its pre-2018 channel near the Lavington wetland.